Recent and New projects at
Phoenix Electrical Engineering Services Limited
Beddington, Croydon
A new green waste
composting facility started February 2004 completed July 2004.
Phoenix won the contract to Design & Build the complete electrical and
automatic controls system for the six composting tunnels. Each tunnel has a
430 cubic metre capacity with its own independent cycle. All design work was
undertaken in house including the electrical installation, control panel and
PLC programming. The operator interface is by way of our Dlog SCADA package.
Attlebridge, Norwich
A small Leachate
treatment works that started in April 2004 and completed in
July 2004.
Another Design & Build project to treat landfill waste water.
Adswood and Barlow Hall
Two Methane stripping plants in Stockport
Luton, Bedfordshire
Modifications and installation of Dlog SCADA to an installation completed
by Phoenix in 1997
Beddington Control Panel ready for factory testing
before delivery